Power Generation Results (Monthly Power Receipt Volume) for August 2020
erex Group is pleased to announce the power generation volume (monthly power receipt volume) for August 2020 as follows.
erex Group’s Total Monthly Power Receipt Volume for August *1
3 Power Plants Total | 96,560 MWh |
Name of power plant | Tosa Power Plant *2 | Saiki Power Plant | Buzen Biomass Power Plant |
Total Monthly Power Receipt Volume (MWh) | 12,396 | 33,110 | 51,054 |
*1 Each power volume is rounded down to the nearest whole number.
*2 Tosa Power Plant suspended its operations from August 4 to August 5 and from August 24 to August 25 for equipment inspection.
Note) Monthly power receipt volume for Ofunato Power Plant is not disclosed.
erex Group operates the largest-level biomass power plants in Japan, fueled by PKS and wood pellets, with a total output of approximately 220 MW (as of August 2020). In addition, erex Group is working to foster renewable energy under the government’s Feed-in-Tariff for Renewable Energy (FIT) program.
As a leading company in renewable energy, erex Group is committed to continuing to contribute to the realization of a low-carbon society in Japan by planning a total output of approximately 350 MW with six power plants to realize an even more satisfactory energy supply in the future.
Power Generation Results to Date
Name of the Power Plant | Tosa Power Plant | Saiki Power Plant | Buzen Biomass Power Plant | 3 Power Plants Total |
August 2020 | 12,396 | 33,110 | 51,054 | 96,560 |
July 2020 | 9,605 | 32,679 | 43,621 | 85,905 |
June 2020 | 12,694 | 28,602 | 28,952 | 70,248 |
May 2020 | 11,464 | 13,896 | 39,545 | 64,905 |
April 2020 | 2,521 | 29,997 | 15,071 | 47,589 |
March 2020 | 13,335 | 28,008 | 48,372 | 89,715 |