October 2023 Power Generation Results (Monthly Power Receipt Volume)
erex Group is pleased to announce the power generation volume (monthly power receipt volume) for October 2023 as follows.
erex Group’s Total Monthly Power Receipt Volume for October *1
5 Power Plants Total | 99,943 MWh |
Name of the Power Plant | Tosa Power Plant*2 | Saiki Power Plant*3 | Buzen Biomass Power Plant*4 | Nakagusuku Biomass Power Plant | Itoigawa Power Plant*5 |
Monthly Power Receipt Volume (MWh) | 12,093 | 28,939 | 26,420 | 32,491 | 0 |
*1 Each power volume is rounded down to the nearest whole number.
*2 Tosa Power Plant suspended its operations on Oct 29 due to periodic repairs. It was also directed to suppress its output twice in accordance with the “directive to suppress output based on the priority power supply rule”.
*3 Saiki Power Plant was directed to suppress its output 28 times in accordance with the “directive to suppress output based on the priority power supply rule”.
*4 Buzen Biomass Power Plant suspended its operations from Oct 18 to Oct 30 due to periodic repairs. It was also directed to suppress its output 16 times in accordance with the “directive to suppress output based on the priority power supply rule”.
*5 Itoigawa Power Plant suspended its operations from Sep 30 to Nov 7 due to periodic repairs.
Note) Monthly power receipt volume for Ofunato Power Plant is not disclosed.
erex Group operates the largest-level biomass power plants in Japan, fueled by PKS and wood pellets, with a total output of approximately 269 MW (as of the end of October 2023). In addition, erex Group is working to foster renewable energy under the government’s Feed-in-Tariff for Renewable Energy (FIT) program.
erex Group is committed to contributing to the prevention of global warming and the realization of a de-carbonized society by aggressively promoting businesses that utilize renewable energy, centering on biomass business, both in Japan and overseas.
Power Generation Results to Date (Unit: MWh)
Name of the Power Plant | Tosa Power Plant | Saiki Power Plant | Buzen Biomass Power Plant | Nakagusuku Biomass Power Plant | Itoigawa Power Plant | 5 Power Plants Total |
October 2023 | 12,093 | 28,939 | 26,420 | 32,491 | 0 | 99,943 |
September 2023 | 12,689 | 30,513 | 46,497 | 30,806 | 51,608 | 172,113 |
August 2023 | 12,708 | 31,299 | 47,881 | 29,594 | 52,696 | 174,178 |
July 2023 | 11,559 | 32,400 | 48,376 | 32,380 | 37,469 | 162,184 |
June 2023 | 12,679 | 29,427 | 44,867 | 31,349 | 0 | 118,322 |
May 2023 | 8,857 | 27,554 | 13,268 | 26,441 | 4,910 | 81,030 |