April 2026 Power Generation Results (Monthly Power Receipt Volume)

erex Group is pleased to announce the power generation volume (monthly power receipt volume) for April 2026 as follows.

erex Group’s Total Monthly Power Receipt Volume for April 2026

4 Power Plants Total 54,730 MWh
 
Name of the Power Plant Saiki Power Plant Buzen Biomass Power Plant Nakagusuku Biomass Power Plant Itoigawa Power Plant
Monthly Power Receipt Volume
(MWh)
28,566 21,812 4,352 0
Outage Period April 16-May 7
(periodic inspection)
April 1-26
(periodic inspection)
April 1-30
(supply-demand adjustments)

Note) Each power volume is rounded down to the nearest whole number.

Monthly power receipt volume for Ofunato Power Plant is not disclosed.

Tosa Power Plant has been suspending its operations since September 1, 2024.


Power Generation Results to Date (Unit: MWh)
Name of the Power Plant Saiki Power Plant Buzen Biomass Power Plant Nakagusuku Biomass Power Plant Itoigawa Power Plant 4 Power Plants Total
April 2026 28,566 21,812 4,352 0 54,730
March 2026 30,073 44,868 30,998 0 105,939
February 2026 28,037 42,643 28,559 0 99,239
January 2026 32,648 48,630 31,994 0 113,272
December 2025 33,240 29,322 32,395 0 94,957
November 2025 5,998 45,497 30,986 0 82,481
 

Note:
This document is an English translation of the original Japanese language document and has been prepared solely for reference purposes. No warranties or assurances are given regarding the accuracy or completeness of this English translation. In the event of any discrepancy between this English translation and the original Japanese language document, the original Japanese language document shall prevail in all respects.